MDT: U.S. Highway 2 paving won’t be until after Labor Day

Print Article

Traffic on U.S. Highway 2 could be downright miserable this summer as it's slated for reconstruction through the city.

Bob Vosen of the Montana Department of Transportation official told city leaders Monday that paving U.S. Highway 2 through the Columbia Falls won’t happen until after Labor Day.

That’s welcome news for businesses and residents who were worried the road work was going to start in late July and run through the summer. Having said that. MDT would like to see the paving done at night. It not only makes dealing with traffic easier, it makes for a betting surface, since there won’t be traffic on the new asphalt.

The city would have to approve the measure and the city council will likely take it up at next week’s board meeting. The city has already allowed for extended hours on the project from 6 a.m. to 10 p.m. The contractor will likely want to pour concrete for the new sidewalks later in the day as well, to avoid conflicts with businesses and traffic.

Vosen and other MDT officials sat down with city leaders to hash out the details on the planned road construction and to clarify the project’s scope, as there has been some misinformation of the project since it was first announced a few weeks ago.

Vosen said MDT expects the project, which will run from the Flathead River Bridge to North Hilltop will start Aug. 14. But the work will first center on sidewalks and curbing — there’s about a mile and half of sidewalk and curb work included in the project.

That will be the first of the work to start in August.

The existing sidewalks will remain the same width, but new sidewalks will be wider — 7.5 feet and the light poles will be taken out of the middle of the sidewalks and moved to the edge of the right-of-way.

MDT asked the city for set dates for festivals and other events that will be going on while construction is taking place so they can write them into the contract. That way the contractor knows to avoid the area at that time. For example, the Community Market is every Thursday at the Coop.

The later start might mean the project doesn’t get completed this year, however, Vosen warned. The roughly $3 million project is expected to take between 90 and 110 days, which would push it into mid-November, where snow becomes an issue.

Print Article

Read More Local News

Park plows 19 miles up west side of Sun Road; on east side, Two Medicine Valley saw several more feet of new snow in past week

April 20, 2018 at 1:43 pm | Hungry Horse News Glacier National Park plow crews in the past week are now at the 19-mile mark on the west side of the Going-to-the-Sun Road, but on the east side, they continue to struggle with new snowfall. Crews ...

Comments

Read More

Wilderness pioneer Stuart Brandborg dies

April 19, 2018 at 4:22 pm | Hungry Horse News Wilderness advocate Stuart Brandborg of Hamilton died April 15. He was 93. In the early 1960s, Brandborg worked under Howard Zahniser, the executive director of the Wilderness Society, on the origin...

Comments

Read More

Yesterdays: Everyone pitched in to patch city streets

April 19, 2018 at 4:18 pm | Hungry Horse News 70 years ago April 16, 1948 Crews had to plow through a snowslide on the North Fork Road where the Glacier View Dam was proposed. At last report, there was 23 inches of snow at Big Creek. The Glaci...

Comments

Read More

Council approves new drive-through coffee shop

April 18, 2018 at 7:07 am | Lake County Leader Columbia Falls will soon have a new drive-through coffee shop as the city council unanimously approved a conditional use permit Monday for Three Byrd’s Properties to place one adjacent to O’Brien’s L...

Comments

Read More

Contact Us

(406) 892-2151
PO BOX 189, 926 Nucleus Avenue
Columbia Falls, MT 59912

©2018 Hungry Horse News Terms of Use Privacy Policy
X
X